T22-1556 East Arnhem Region - Galiwinku Stage 2 - Subdivision Civil Works and Services Construction 

VALUE <$9M

SUMMARY

AKJ Services have successfully delivered a remote 27 lot subdivision at Galiwinku which involved:  

​

·    Earthworks (cut 6,910m3 fill 770m3 and import 2,750m3) 
·    Concreting (829 m3)
·    Stormwater Drainage (300 lin. Meters) 
·    Water Reticulation and Connections (651 lin. Meters) 
·    Sewer Reticulation and Connections (544 lin. Meters) 
·    Electrical Reticulation and Connections 
·    Telecommunications (733 lin. Meters) 
·    Erosion and Sediment Control 
·    Road Construction (approx. 3,677m2 of seal) 
·    Landscaping (approx.18,500 m2) 